Phase I All siding ,flashing ,gutters Downspouts, A/C platforms, painting of trim and partial painting of platforms, installations of carport shed roofs have been completed as of March 30,2000 .Patio fences are substantially completed. All punch out to be completed by April 4th, 2000.
|
|